Set default Gantt chart settings for the team

One of the features of Ganttify is that each user can customize Gantt charts to their liking: hiding, showing, and resizing columns, choosing Zoom levels, setting a date format, etc.

While this is great for individual users, you may want to ensure that everyone is looking at the same Gantt chart with the same columns visible/hidden and the same zoom level.

As a team owner, you can choose to set customizations you have made with the rest of the Ganttify team. It’s straightforward to do:

  • Open the Timeline settings dialog by clicking the gears icon in the top left of the Gantt chart.
  • Click on the “Team” tab.
  • Here, you check “Set my timeline settings as default for team members
  • Click on “apply changes
Set default timeline settings for team
Set default timeline settings for team

When a team member opens this Gantt chart, they’ll automatically see the default settings you have set and can start working with the project’s timeline instead of having to customize the Gantt chart first.

Ready to dive in?

Try Ganttify 14 days for free